Dexon Technology holds a 94% first run inline inspection (ILI) success rate with 471 pipelines inspected to date. Dexon’s Unpiggable Inspection Archive features a selection of unpiggable or ‘challenging’ ILI case studies from Dexon’s archive.

A team of Dexon pipeline engineers recently completed the inspection of a 32 km 3 in. unpiggable or ‘challenging’ underground petrochemical distribution pipeline running from an onshore processing facility to a port on the South American coast. This was the first inspection for this pipeline in its 30-year life due to the challenging nature of the inspection. The small diameter of the pipeline meant that specialised tool development, modification, and testing were required at Dexon’s headquarters in Thailand prior to the inspection, with onsite client verification performed in early December of 2022.

The challenge

  • 3 in. small-diameter inspection of a long-range 32 km distribution pipeline (typical 3 in. transfer lines run for only a few hundred meters in a single plant).
  • Pipeline characteristics such as weld penetration can cause significant internal diameter restrictions in small-diameter pipelines.
  • A lack of previous inspection data with this being the first inspection for this pipeline.
  • Online inspection.

The small diameter of the pipeline paired with the long inspection length of 32 km made this inspection challenging. Typical 3 in. transfer pipelines run for a few hundred meters (200 - 400) within a single plant, making this run 106 times longer than a typical 3 in. inspection run. While weld penetration and other characteristics in small-diameter pipelines can cause significant reductions in the pipeline’s internal diameter. Limited space inside the tool bodies caused by the small diameter of the pipe required customised design, modification, and testing of the tool prior to the inspection. Providing sufficient battery life and data storage to complete the inspection. In addition, this was the first inspection for this pipeline in its 30-year lifetime causing uncertainty around the geometric condition of the pipeline in underground sections which could possibly lead to a stall. The client required the inspection to be completed online, reducing the impact on operations.

The solution

  • Customised design and modification of Dexon Technology’s existing 3 in. small diameter UT-MC fleet.
  • Customisation of Dexon’s onsite test loop configurations to replicate inspection conditions.
  • Extensive long-range durability testing at Dexon’s onsite test yard.
  • Onsite client inspection data verification.
  • Comprehensive cleaning and gauging to adequately gauge the geometric condition of the pipeline prior to inspection.

Dexon Technology’s research, development, and engineering department offers customised tool developed as part of Dexon’s Unpiggable or ‘Challenging’ Pipeline Inspection Programme. A pig from Dexon’s existing 3 in. UT-MC fleet was modified to complete the inspection. Providing additional battery units to accommodate the long operating time of the inspection. With the pig traveling at approximately 1 m/sec. over the 32 km distance for a total inspection time of 9 hours from launching to receiving. Dexon Mechanical Solutions (DMS), Dexon’s pipeline maintenance and repair division, performed alterations to Dexon’s onsite test loop configurations to replicate inspection conditions and allow for extensive long-range durability testing prior to the inspection. Onsite client inspection data verification was performed in early December of 2022 with a team of pipeline operators visiting Dexon’s headquarters in Thailand. Thorough cleaning and gauging were performed onsite to adequately determine the geometric condition of the pipeline to avoid a stall in the line.

Read the article online at: https://www.worldpipelines.com/product-news/28022023/world-first-unpiggable-ili-completed/

You might also like

CO2 systems, studies and solutions

Alessandro Terenzi, Giorgio Arcangeletti, Enrico Bonato, Elvira Aloigi, Lorenzo Maggiore, and Annalisa Di Felice, Saipem S.p.A., offer an overview of the challenges and opportunities for CO2 pipelines in the energy transition, drawing on offshore and onshore case studies.

 
 