Environmental decision for Baltic Pipe project
Published by Lydia Woellwarth,
Editor
World Pipelines,
On 4 February 2019, the Regional Director for Environmental Protection in Gorzów Wielkopolski issued a decision on environmental conditions for the project under implementation by GAZ-SYSTEM ‘Construction of the Goleniów - Lwówek DN1000 gas pipeline.’ This is one of the five investments planned within the Baltic Pipe project in Poland.
The pipeline will be approximately 191 km long, its nominal diameter will be 1000 mm and its operating pressure 8.4 MPa. It will be constructed along currently existing gas pipeline Szczecin-Lwówek located in three provinces: Zachodniopomorskie, Lubuskie and Wielkopolskie, and will cover 15 communes: Goleniów, Maszewo, Stargard, Dolice, Przelewice, Pelczyce, Strzelce Krajenskie, Zwierzyn, Santok, Deszczno, Skwierzyna, Przytoczna, Pszczew, Miedzychód and Lwówek.
The planned gas pipeline will ultimately be divided into two implementation sections:
- Section 1: Goleniów-Ciecierzyce, approximately 122 km long.
- Section 2: Ciecierzyce-Lwówek, approximately 69 km long.
The purpose of this investment is to increase the volume of gas offtake from the Baltic Pipe submarine gas pipeline and the LNG Terminal in Swinoujscie. Its implementation will constitute an important element of the North-South Gas Corridor in Europe.
The Baltic Pipe project is recognised by the European Commission as a Project of Common Interest (PCI). This status is granted to infrastructure projects aimed at strengthening the European internal energy market, which pursue the objectives of EU's energy policy that involve providing affordable, secure and renewable energy. The Baltic Pipe project is included in all existing PCI lists adopted in 2013, 2015 and 2017, respectively.
Baltic Pipe is a strategic project aimed at creating a new gas supply corridor in the European market. For the first time in history, it will make it possible to transport gas directly from deposits located in Norway to the markets in Denmark and Poland, as well as to customers in neighbouring countries.
The main objectives of the project include strengthening the diversification of supplies, integrating the gas market, price uniformity as well as security of supply primarily in Poland and Denmark, as well as in Central and Eastern Europe and in the Baltic Sea region.
Read the article online at: https://www.worldpipelines.com/project-news/12022019/environmental-decision-for-baltic-pipe-project/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Eni and the UK Government reach financial close for the Liverpool Bay CCS project
The project foresees the efficient repurposing of part of the offshore platforms as well as 149 km of onshore and offshore pipelines, and the construction of 35 km of new pipelines to connect industrial emitters to the Liverpool Bay CCS network.