Transneft PCD lays siphon during oil pipeline construction

Published by , Editor
World Pipelines,


Transneft PCD has pulled a siphon under the Kryukovsky discharge canal, as part of the project for construction of the Novovelichkovskaya-Krasnodar oil trunk pipeline’s line portion for supplying sour crude oil. The siphon’s length totalled 390 m.

A siphon is an oil pipeline section laid across a natural or a man-made obstacle: under the stream bed of a river or a channel, along the bottom of a deep gully, under a motor road or a railway. A siphon is comprised of several pipes that are first welded into a string (a stalk) and then pulled through a prepared well.

The underwater crossing under the Kryukovsky discharge canal was made by directional drilling, which envisioned an extra dry pigging of the siphon yet at the preparation phase. An inline inspection tool (a combined magnetic flaw detector manufactured by Transneft Diascan) was run through the pipeline at a mounting platform after hydraulic testing of the welded stalks. No defects were detected.

Preparations for the second phase of hydraulic testing are currently underway.

Inline inspection of another siphon to be pulled under MK-2 Discharge Canal in Krasnodar Territory has also been completed within the project. 329 m of the pipeline with the diameter of 530 mm was inspected. No defects were detected.

All construction and installation works at the underwater crossings are scheduled to be completed in August 2018.

Read the article online at: https://www.worldpipelines.com/project-news/06072018/transneft-pcd-lays-siphon-during-oil-pipeline-construction/