Alexey Miller: Yamal is the future of the Russian gas industry

World Pipelines,


A new gas facility (GP-1) was commissioned at the Bovanenkovskoye field.

Taking part in the commissioning ceremony were Alexey Miller, Chairman of the Gazprom Management Committee, Dmitry Kobylkin, Governor of the Yamal-Nenets Autonomous Area, heads of the Company’s structural units, subsidiaries and contracting agencies.

Russian President Vladimir Putin commanded to put onstream the gas facility.

Gazprom gradually builds up its production capacities in the Bovanenkovskoye field and develops the Cenomanian-Aptian deposits. The annual design capacity of the new gas facility (GP-1) is 30 billion cubic meters. As a comparison, it is more than the Company will be producing from the Chayandinskoye field, the largest one in Yakutia.

Innovation technologies and engineering solutions were applied while building the new gas facility. In particular, the single technical infrastructure is used for extracting gas from productive deposits at different depths – Cenomanian (520 - 700 m) and Aptian-Albian ones (1200 - 2000 m). It saves construction expenditures and increased field productivity.

The technical operations are highly automated and unmanned technologies are used at the facility. Gas treatment is carried out applying the most advanced and environmentally clean method of low temperature separation with the use of domestic turbo expanders.

In the process of construction special attention was paid to preserving the unique nature of Yamal. Process facilities occupy the least possible area, while vapour-liquid heat stabilisers and insulated pipes for wells reduce the impact on the permafrost. In-plant recycling systems eliminate water and soil pollution.

Gas from the new gas facility is fed into the Unified Gas Supply System of Russia via the Bovanenkovo – Ukhta gas trunkline system (GTS) under the pressure of 11.8 MPa (120 Ata). It was possible to reach the record pressure for onshore gas pipelines mainly due to unique domestic 1420 mm pipes made of K65 (X80) steel and with a smooth interior coating, developed on Gazprom’s order. Currently, the construction of GTS’ second string is underway.

The Yamal Peninsula has a strategic importance for the evolution of the Russian gas industry, and this requires building greenfield production facilities in the hash Yamal climate as well as constructing motor roads, power plants, a rail connection and an airport. Explored and provisionally estimated gas reserves there exceed 16.7 trillion m3. In the long view Yamal will be among three biggest gas production centres of Russia with the potential annual output reaching 310 to 360 billion m3 of gas by 2030 – over one-third of forecasted gas production in Russia for that period.

“The development of an unparalleled gas production centre is well underway in Yamal, in harsh Arctic latitudes. The annual design capacity at Bovanenkovo has already amounted to 90 billion m3 of gas. It is commensurate with the volume supplied by Gazprom to Germany, Turkey and Italy last year, and this is not the full productivity yet. Yamal is the future of the Russian gas industry,” said Alexey Miller.


Adapted from press release by Hannah Priestley-Eaton

Read the article online at: https://www.worldpipelines.com/business-news/05012015/alexey-miller-yamal-is-the-future-of-the-russian-gas-industry/