Trans Mountain continues construction on Expansion Project

Published by , Editorial Assistant
World Pipelines,


Construction is underway and progressing along the Trans Mountain Expansion Project with close to 8000 people working in communities across British Columbia and Alberta.

Claims made through the media with regards to a “four-month stop work order on pipeline construction” are false.

Trans Mountain was issued a compliance order by Environment and Climate Change Canada (ECCC) after an inspector was alerted to a hummingbird nest found nearby construction activity in the Brunette River area of Burnaby, BC. The Order applies to the specific “work package,” which is an area covering approximately 1000 metres of private land between the Trans-Canada Highway and a rail corridor and restricts certain construction activities. Trans Mountain will proceed with any work within the 1000 m area not subject to restrictions of the Order. Work on the Expansion Project continues in all other regions and areas of the Lower Mainland in British Columbia and in Alberta.

Trans Mountain is engaging with regulators to review federally approved environmental programmes and mitigation measures in place to prevent disturbance to migratory birds during the nesting period.

Trans Mountain is working with ECCC to determine when work in the area subject to the Order can recommence. They are confident all of their approved environmental mitigation procedures are effective and will seek to have the restrictions under the Order lifted as soon as appropriate and according to the law.

Claims of increased Expansion Project costs related to the work restriction in this segment of Burnaby are unfounded. There has been no change to Trans Mountain’s projected completion date for the Expansion Project of December 2022.

 

Read the latest issue of World Pipelines magazine for pipeline news, project stories, industry insight and technical articles.

World Pipelines’ May 2021 issue

The May issue of World Pipelines includes a regional report on Canada’s oil and gas sector, as well as technical articles on integrity management software, leak detection, NDT, and project case studies. Don’t miss our feature on young pipeliners, in which World Pipelines’ Senior Editor Elizabeth Corner interviews the winners of the John Tiratsoo Award for Young Achievement, awarded by Young Pipeliners International, in partnership with PPIM.

Read the article online at: https://www.worldpipelines.com/project-news/30042021/trans-mountain-continues-construction-on-expansion-project/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Canada pipeline news