Coquihalla construction updates
Published by Sara Simper,
Editorial Assistant
World Pipelines,
Updates from the Trans Mountain Expansion Project on Coquihalla Summit to Othello Road, Othello Road to Popkum and Kamloops to Merritt.
Coquihalla Summit to Othello Road pipeline construction
Work is underway in a series of phased activities along the pipeline right-of-way. This could include; surveying, flagging and staking the right-of-way, mobilisation of crews and equipment, preparing the right-of-way, clearing and grading, delivery and staging of pipe, trenching, welding, lowering of pipe, backfilling and restoration of the right-of-way.
Othello Road to Popkum pipeline construction
Work is underway in a series of phased activities along the pipeline right-of-way. This could include; surveying, flagging and staking the right-of-way, mobilisation of crews and equipment, preparing the right-of-way, clearing and grading, delivery and staging of pipe, trenching, welding, lowering of pipe, backfilling and restoration of the right-of-way.
Kamloops to Merritt pipeline construction
Work is underway in a series of phased activities along the pipeline right-of-way. This could include; surveying, flagging and staking the right-of-way, mobilisation of crews and equipment, preparing the right-of-way, clearing and grading, delivery and staging of pipe, trenching, welding, lowering of pipe, backfilling and restoration of the right-of-way.
Read the article online at: https://www.worldpipelines.com/project-news/28032022/coquihalla-construction-updates/
You might also like
Decouplers making a difference
Jay Warner, Dairyland Electrical Industries, USA, Jerzy Sibila and Jerzy Mossakowski, CORRSTOP, Poland, explain how AC mitigation is a proven technique to solve AC interference problems on pipelines, referring specifically to the use of DC decouplers.