Nord Stream 2 pipelay vessel making progress
Published by Lydia Woellwarth,
Editor
World Pipelines,
The pipelay vessel CASTORO 10 (C10) is currently located off Rügen to tie together the two ends of a Nord Stream 2 pipe string laid last year on the seabed. The two sections will be connected above water with a weld seam.
In what is known as an above-water tie-in (AWTI) both pipe ends will be lifted out of the water and then cut, aligned and welded together from a working platform attached to the C10. The weld seam is ultrasonically tested and coated with an anti-corrosion protection. Afterwards, the pipe string will be placed on the Baltic seafloor in a slight arc.
Including all preparation and follow-up work, the procedure takes two to three weeks. With optimal weather conditions and smooth operations, the works above water can be completed within just a week.
For the duration of the works, Nord Stream kindly ask all mariners in the area for increased attention in the interest of their safety. The C10 is situated northwest of the ‘Landtief’ approach and positioned with eight anchors. Due to the anchor pattern as well as diving works, a safety distance of at least 1000 m from C10 must be observed.
Work on the Nord Stream 2 pipeline continues to proceed as scheduled. Altogether more than 1700 km (over 70%) of both pipe strings have been laid in accordance with the existing permits in the waters of Germany, Sweden, Finland and Russia.
Read the article online at: https://www.worldpipelines.com/project-news/13082019/nord-stream-2-pipelay-vessel-making-progress/
You might also like
North Sea Midstream Partners supports start-up of compression for Breagh field
Gas from the Breagh field is exported through the 110 km Breagh pipeline to TGPP – which is owned and operated by NSMP – where gas is processed and delivered into the National Transmission System.