TC Energy's Coastal GasLink seeks damages from contractor

Published by , Senior Editor
World Pipelines,


Coastal GasLink, a Canadian natural gas pipeline partnership operated by TC Energy, is seeking CAN$1.2 billion (US$737 million) from one of its main contractors for construction delays and may be liable for a similar amount if an arbitrator rules against it, court documents showed ahead of a hearing this month (Reuters reports).

Construction of the CAN$14.5 billion Coastal Gas-Link (CGL), which TC began planning in 2012, finished in October at more than double its original budget. Private equity firm KKR & Co. and Alberta pension manager AIMco jointly own 65% of the limited partnership and TC owns the remaining 35%.

The dispute over the project that will supply Canada's first LNG export facility around 2025 highlights the extreme difficulties operators face in building Canadian pipelines. The Canadian government-owned Trans Mountain pipeline expansion, which aims to boost oil exports, has also faced delays and soaring costs, reports Reuters.

The 670 km (416 mile) CGL through British Columbia's Rocky Mountains to the Pacific coast was delayed by mudslides, a six month pandemic work stoppage, sometimes violent protests and steep terrain that forced TC to use ski lifts to transport pipe.

CGL also terminated contractor Pacific Atlantic Pipeline Construction's (PAPC) contract last year alleging poor performance and is claiming CAN$1.2 billion for the cost of finding new contractors, Blaine Trout, TC's Vice President in charge of CGL, said in court on 17 November.

The two parties have gone to court in Alberta with CGL arguing it is legally entitled to draw on a CAN$117 million letter of credit, issued by HSBC to CGL as a performance guarantee for PAPC.

The Alberta court case comes ahead of the two par-ties facing off in International Chamber of Commerce arbitration in November 2024 over whether PAPC defaulted on its contract or was wrongfully terminated.

On 19 October, an Alberta court granted an injunction request from PAPC and its parent company, Italian contractor Bonatti, forcing CGL to withdraw its call on the letter of credit, pending the 19 December hearing. The letter of credit expires in early 2024.

TC said in a statement that the cost of PAPC's alleged failure to perform significantly exceeds the amount of the letter of credit.

"Coastal GasLink is committed to enforcing its contractual rights and is actively pursuing cost recoveries as it is entitled to," TC Energy said.

PAPC alleges its work was undermined by CGL's thousands of design changes during construction and protests that CGL could not control.

Greg Cano, PAPC's Chief Operations Officer, told Reuters that TC tried to force PAPC to accelerate construction, which would have required the con-tractor to almost double its staffing and equipment on site, without paying for the extra cost.

Cano, who previously worked for TC, said he has never seen such a dispute in his 45 years building pipelines.

If the Alberta judge allows CGL to call the letter of credit, financial losses to PAPC and Bonatti could snowball, the companies said in court.

They may be unable to pay the cost of arbitration, complete current projects or bid on others, resulting in PAPC's possible insolvency, said Bonatti CEO Andrea Colombo, in an affidavit.

PAPC is seeking up to CAN$1 billion in its arbitration proceeding.

 

 

Read the latest issue of World Pipelines magazine for pipeline news, project stories, industry insight and technical articles.

World Pipelines’ December 2023 issue

The December 2023 issue of World Pipelines includes a keynote feature on cyber security, covering safeguarding against cyberattacks and effectively protecting critical infrastructure, taking operational security into account. This issue also includes an interview with Winn & Coales International about how the company is celebrating its 140th anniversary, as well as articles focused on hydrogen, pipeline machinery, flow and metering and monitoring.

Read the article online at: https://www.worldpipelines.com/project-news/12122023/tc-energys-coastal-gaslink-seeks-damages-from-contractor/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Canada pipeline news Natural gas pipeline news


 

World Pipelines is not responsible for the content of external internet sites.