DEQ issues stop work on two-mile section of Mountain Valley pipeline
Published by Aimee Knight,
Editorial Assistant
World Pipelines,
The Virginia Department of Environmental Quality (DEQ) has issued a stop work instruction to Mountain Valley Pipeline, LLC (MVP). The instruction is based on issues identified during DEQ inspections that cite insufficient erosion and sediment controls on approximately a two-mile section of the project in Spread H in Montgomery County.
Based on a DEQ inspection conducted on Thursday 1 August, the agency has determined that an imminent and substantial adverse impact to water quality is likely to occur as a result of land-disturbing activities. Specifically, MVP has failed to construct and maintain erosion and sediment control or pollution prevention measures in accordance with approved site-specific plans and/or the erosion and sediment control measures that have been installed are not functioning effectively and MVP has not proposed any corrective action.
Work in this section will be suspended until these corrective actions are installed and approved by DEQ through field inspection and verification. MVP must stop all land disturbing activities in this area including clearing, grading and trenching activities in the designated area. The only activity currently authorised in this area is work necessary to install and maintain erosion control devices as required by the approved site-specific erosion and sediment control plans, and the annual standards and specifications.
“We are appalled that construction priorities and deadline pressures would ever rise above the proper and appropriate use of erosion control measures,” said DEQ Director David Paylor. “DEQ will continue to monitor and inspect all ongoing work to ensure continued compliance and protection of Virginia’s natural resources.”
Read the article online at: https://www.worldpipelines.com/project-news/06082019/deq-issues-stop-work-on-two-mile-section-of-mountain-valley-pipeline/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Eni and the UK Government reach financial close for the Liverpool Bay CCS project
The project foresees the efficient repurposing of part of the offshore platforms as well as 149 km of onshore and offshore pipelines, and the construction of 35 km of new pipelines to connect industrial emitters to the Liverpool Bay CCS network.