Skip to main content

Saudi Aramco adopts cutting-edge pipeline practices

Published by , Editor
World Pipelines,


The worldwide adoption of reinforced thermoplastic pipe (RTP) in construction projects dates back to the early years of the 21st century as the technology drove cost saving initiatives by providing sustainable corrosion control measures.

Saudi Aramco adopts cutting-edge pipeline practices

However, the early uses of RTP technology were constrained by the application limitations of the manufactured pipes, which was reflected in maximum sizes, fluid pressures, and temperatures of the process designs. These application limitations have been progressively eased by advances in materials and manufacturing technology, requiring companies to stay abreast of developments in the field.

At Saudi Aramco, this is not necessarily a straightforward process. In larger companies, interdependent departments play various roles to validate, approve, and collaborate with vendors in an effort to reassure the safety and reliability of adopted technologies. In this context, Project Management and Engineering Services have had success in progressively deploying RTP in Onshore Maintain Potential Projects Department (OMPPD) oil and water service projects, working with vendors and other departments to introduce proven technological advancements that have produced significant savings for Saudi Aramco.

Early adoption

OMPPD first deployed RTP back in 2015 in the Khurais and Central Arabia areas. The project scope included a 142 km length of 4 in. fibre reinforced RTP pipe with two suppliers where the oil applications required low design conditions (i.e., 1500 psi and 140°F). As a result of prudent economic analysis, significant savings were achieved by avoiding a single 6 in. pipe, which was available from a single supplier, and using dual 4 in. pipes. The savings were increased further by a three-week reduction in the construction schedule relative to the use of solid corrosion resistant alloy. However, due to the constraints of technology and manufacturer capabilities, RTP could not be adopted in water service projects where the parameter envelop is as high as 3000 psi.

Applications expansion

The forecast of 150 km length of RTP pipe in water injection applications for the Southern Area Oil Operations (SAOO) and Khurais areas laid the foundation for OMPPD to search the market for suppliers to provide 6 in. pipe that could withstand 3000 psi. With the support of the Consulting Services Department (CSD), the Pipelines Project Department, and other organisations, a supplier was introduced to expand the applications that can leverage the cost savings of RTP using steel reinforcement technology. However, the sole source strategy did not support the economic business case of an RTP alternative as more suppliers were needed to reduce the cost through competitive bidding and to increase the bargaining power of the company.

Not long after, in 2017, the extensive research and capabilities verification efforts resulted in another supplier being qualified and added to RTP approved vendors. After a competitive bidding process, an order was successfully placed.

Continuous cycle

Project Management and Engineering Services continues to work to increase RTP applications in OMPPD, but it requires continuous market intelligence of technological advances and being aware of vendors’ current capabilities – all in co-ordination with other organisations.

By doing this, a new supplier has been identified that can produce an application to handle up to 2250 psi at 221°F. CSD is currently working with the vendor to ensure completion of the required qualification tests and arrange a field trial in collaboration with SAOO.

As the importance of project performance in terms of schedule and capital expenditure remain critical to Saudi Aramco business, facility life cycle costs are a paramount requirement for OMPPD. Progressively adopting RTP is a definite means to helping meet these scheduling and cost improvement goals.

Image courtesy of Saudi Aramco.