Wouri River Pipe laid to Bonaberi Shore

World Pipelines,


Victoria Oil & Gas Plc, the emerging Cameroon utility company, announces that 678 m of gas pipe has successfully been laid under the Wouri River to the northern Bonaberi shore in Douala, Cameroon's major industrial city.

The laying of the 400 mm pipe under the Wouri River extends the reach of the Gaz du Cameroun (GDC) gas supply network to a new industrial customer hub within Douala. To date, GDC has laid 860 m of 400 mm pipeline and 1129 m of branch spurs in the Bonaberi-Magzi Estate area. This network will shortly be connected to the main pipeline, commissioned and ready to supply gas to new customers, following safety checks and flow testing.

Following this extension to the network, there are now three customers with signed gas supply agreements in place. GDC, working ahead of the pipe-laying under the river, has already converted burners and completed downstream engineering work to these thermal customers so that they are now ready to be supplied with gas, increasing daily gas consumption levels and GDC's revenues.

Further RNS announcements will be made following the successful connection of customers on the Bonaberi shore.

Kevin Foo, Chairman, said: "This crossing under the Wouri River is truly an outstanding achievement by our contractor Britanica and our GDC engineering team. We overcame many challenges and pulling almost 700 m of heavy gauge pipe under a major tidal shipping channel is another first in Cameroon for GDC. The pipe will be pressure tested over the next 10 days and once approved will be connected to the first customers in Bonaberi."


Adapted from press release by Hannah Priestley-Eaton