South Stream progressing in strict compliance with the schedule

World Pipelines,


It was pointed out that South Stream was progressing in strict compliance with the schedule.

Progress

The Bulgarian Republic will soon sign contracts for material and equipment procurement as well as for installation works, personnel training and commissioning of a pipeline section. Similar activities are being carried out in the Republic of Serbia. The main construction operations in Bulgaria and Serbia are scheduled for this summer,

In Hungary, FEED is currently underway in addition to the spatial planning and environmental impact assessment (EIA) activities. In the Republic of Slovenia the spatial planning and EIA are also in progress; bids to design the Slovenian section will be announced before the beginning of summer.

The Republic of Croatia goes on generating the Shareholders Agreement of the joint project company; the draft contract and scope of work for devising the project documentation are being negotiated.The investment concept is being developed for constructing a gas branch to the Republic of Macedonia

Intergovermental agreements for the project have been signed with all the above mentioned countries.

In the Republika Srpska an intergovernmental agreement is being drafted to provide co-operation during the construction and operation of South Stream's branch and power facilities.

Upon the initiative of the Austrian party, Gazprom started examining the possibility of creating a gas pipeline section in Austria simultaneously with the Slovenian section being constructed.

South Stream's offshore section

Arrangements for laying South Stream's offshore section are in full swing. The companies that won the open tender are intensely building up the pipe production for the first string. The agreement was signed for the gas pipeline construction as well as for the process facilities construction and the landfalls infrastructure development for four offshore gas pipeline strings in Russia and Bulgaria. Pipe supply to Bulgaria will start as soon as this May. In June the operations will start on the Russian coast, in July – in Bulgaria. The offshore pipeline laying will begin this autumn.

The meeting stressed that some 8500 jobs would be created in Bulgaria, Serbia, Hungary, Slovenia and Croatia to build and subsequently operate South Stream.First gas will be delivered via the gas pipeline in late 2015.

Operations are well underway at the Russkaya main compressor station, which is South Stream's starting point. It will be the world's leader in terms of installed capacity, which is 448 MW. The core process equipment, i.e., gas compressors and treatment units, are being installed at the station. This work will be completed in 2014.

Southern Corridor gas trunkline system

Large-scale construction is currently in process at the Southern Corridor gas trunkline system to feed gas to South Stream. On the western route (Phase 1 of the project) 576 km of pipes (65% of its total length) have been welded and laid. Many gas pipeline sections are being tested. Compressor stations (CS) are under construction. The core process equipment is being installed at the Kazachya CS and the Korenovskaya CS, which will be completed in the first quarter of 2015; the foundation is being constructed at the Shakhtinskaya CS.

Phase 2 of the project

Preparations for the eastern route (Phase 2 of the project) construction have begun.

With a view to supply the required volumes of gas via the western route, the Urengoy – Novopskov gas pipeline is being expanded at the Petrovsk – Pisarevka section. By now, some 170 km of the gas pipeline have been overhauled.

The upgrade of the three out of six compressor stations – Yekaterinovka, Bubnovka and Pisarevka – is in progress with a purpose to increase their capacities. The core process equipment is being installed there. The Yekaterinovka CS and the Bubnovka CS upgrade is to be finished by late 2014, the Pisarevka CS – in the second quarter of 2015. Once the upgrade is over, the Bubnovka CS and the Yekaterinovka CS capacities will total 96 and 64 MW respectively.

“Only South Stream may offer now extra guarantees of energy security to Europe,” said Alexey Miller.


Adapted from press release by Hannah Priestley-Eaton

Read the article online at: https://www.worldpipelines.com/business-news/29042014/south_stream_progressing_in_strict_compliance_with_the_schedule/

You might also like

Fluxys appointed Belgium's 'hydrogen network operator'

A specially formed subsidiary of gas pipeline operator Fluxys has been appointed Belgium’s “hydrogen network operator”, putting it in charge of building out and operating an H2 pipeline grid in the country.

 
 

Embed article link: (copy the HTML code below):