During its first commercial application, the newly developed Vibro Lifting Tool (VLT) of CAPE Holland has successfully installed four piles in up to 90 m water depth.

This installation is part of the pre-piling project for the Culzean Wellhead Platform jacket, which will be installed next year. The VLT was used as a stabbing tool to install all four piles in one sequence to stable depth through a template without any tool change.

Negating the need for a tool change meant it was possible to install all four piles in just one 12 hr shift to the predicted penetration depths, which resulted in a significant time saving.

CAPE Holland’s comments

CAPE Holland’s CEO Laurens de Neef commented: “this is a major milestone for our company, and has once again shown the potential of the VLT by demonstrating that this approach contributes to improved productivity and safety. It increases the pile installation rates by optimising crane handling operations with an added advantage of reducing the amount of required equipment on deck… I am very proud of our team, who have worked extremely hard over the past year to develop the VLT for its first application.”

Edited press release by Stephanie Roker

Read the article online at: https://www.worldpipelines.com/business-news/27072015/new-vlt-from-cape-holland/

You might also like

Decouplers making a difference

Jay Warner, Dairyland Electrical Industries, USA, Jerzy Sibila and Jerzy Mossakowski, CORRSTOP, Poland, explain how AC mitigation is a proven technique to solve AC interference problems on pipelines, referring specifically to the use of DC decouplers.

 
 

Embed article link: (copy the HTML code below):