North Sea blockage clearance fails

Published by , Editor
World Pipelines,


Serica Energy plc, an independent oil and gas company with production, development and exploration licence interests in the UK North Sea and exploration interests in Ireland and Namibia, hereby provides the following update on the interruption to production at the Erskine field.

As announced on 22 January 2018, during cleaning operations a blockage occurred on the Lomond to Everest pipeline, through which Erskine condensate is exported to market. This caused Erskine field production to be shut-in. The blockage is believed to be due to a deposit of wax in the pipeline. Chrysaor Limited, the operator of this pipeline, has been attempting to resolve this problem but has been unable to achieve a significant breakthrough. Therefore, the decision has been made to cease clearance operations and instead concentrate on accelerating the pipeline bypass programme and on running an extended maintenance programme.

Plans to lay a new 26 km length of pipeline to bypass the zone affected by wax deposits have been progressing. An order was placed with the pipeline manufacturers in February and a route survey has been completed. Approvals for the work from the authorities are expected in July and construction is scheduled for August, with production restart expected in September. Once laid, a proactive cleaning programme will commence in order to maintain the pipeline through high frequency pigging.

As a significant maintenance programme was already planned for this summer, the Lomond operator has taken the opportunity to extend this, performing further, pre-emptive maintenance on the platform whilst it is hydrocarbon free. From 1 May, work will commence to reduce the backlog of maintenance work as well as perform inspections and replace and repair key equipment. This work is designed to improve future performance of the facilities, reducing production interruptions and reducing the length of future shut-downs in the coming years.

Mitch Flegg, Chief Executive of Serica Energy, commented:

“While we are disappointed that efforts by the Lomond field operator to clear wax from the Lomond condensate export line have not been successful we are pleased that plans to achieve a permanent solution for this recurring problem are progressing well.

The operator is taking the opportunity to perform significant extra maintenance work during the planned 2018 Lomond shutdown. This should lead to improved performance later this year and in future years to the long-term benefit of the Erskine field. Although this is expected to extend the Erskine shut in to September, there was no certainty that the clearance work would have been successful but would have still incurred additional ongoing cost. We have the benefit of a strong balance sheet which enables us to fund our share of the pipeline bypass during this period without Erskine production revenues.

One of the key reasons for Serica’s acquisition of BP’s interests in the producing Bruce, Keith and Rhum (BKR) fields is to diversify Serica’s production. The BKR transaction is effective from 1 January 2018 with Serica deriving full benefit from that date. BKR production is unaffected by the Lomond to Everest pipeline problems. The transaction is due to complete late in quarter three this year.”

Read the article online at: https://www.worldpipelines.com/business-news/25042018/north-sea-blockage-clearance-fails/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Europe pipeline news Pipeline pigging news