Pioneering Spirit completes GTA infield pipelay scope
Published by Isabel Stagg,
Editorial Assistant
World Pipelines,
Pioneering Spirit has completed the infield pipelay scope for BP’s ultra-deepwater GTA liquified natural gas project offshore Mauritania and Senegal.
Two months after arriving in the field, production crew welded, scanned and field joint coated the final piece of pipe for the second 16 in. export gas line.
Safely landed in a 2 m target box at 2400 m water depth, the pipeline will be recovered in J-mode configuration to install the termination assembly. To make this happen, the vessel aft has been fitted with a bespoke J-mode frame with a 1000 t load capacity. Designed, built and installed on board in only eight weeks by our engineering and fabrication teams, it typifies Allseas “can do” mentality.
The pipelay scope comprises approx. 75 km of 16 in. export lines and 10 km of 10 in. CRA infield lines, some of the pipeline infrastructure exceeding 2700 m water depth at the deep end! To meet our own ambitious production rate, the main firing line and double jointing facilities on Pioneering Spirit have run in parallel throughout the campaign. Pioneering Spirit will conclude the offshore works by installing the six outstanding flowline termination assemblies.
Allseas Project Manager Laurent Beghin says, “Our Agile approach was key to a quick and efficient start to the project and decision-making process throughout the offshore campaign. Thanks to great collaboration between the onshore and offshore teams, we’ve overcome all challenges faced during the project preparation and execution phases and met all milestones without delay.”
Read the latest issue of World Pipelines magazine for pipeline news, project stories, industry insight and technical articles.
World Pipelines’ February 2024 issue
The February 2024 issue of World Pipelines includes a report on pipeline activity in the UK and Europe, along with technical articles on protecting pipelines during construction, surface preparation, and measuring methane emissions from pipelines. This issue also includes our annual inline inspection Q&A, with contributions from a host of ILI experts.
Read the article online at: https://www.worldpipelines.com/business-news/22022024/completion-of-gta-infield-pipelay-scope/
You might also like
ONEOK announces completion of NGL fractionation and pipeline expansion projects
ONEOK has announced the completion of MB-6, a 125 000 bpd natural gas liquids (NGL) fractionator in Mont Belvieu, Texas, and the full looping of the West Texas NGL Pipeline system.