Baltic Connector compressor station celebration
Published by Lydia Woellwarth,
Editor
World Pipelines,
The topping-out ceremony and the progress of construction work were celebrated at the Baltic Connector project’s compressor and metering station worksite in Inkoo. The topping-out ceremony was held for the worksite personnel on 7 November 2018. Baltic Connector Oy’s President and CEO, Herkko Plit, was the speaker for the developer, and Nina Lindström, Managing Director of RTA Yhtiöt Oy, spoke on behalf of the builder.
“It is great to be able to celebrate the project’s next milestone. We are involved in making sure that the Finnish gas market can open at the beginning of 2020. Thanks to competent project management and capable contractors, the project has progressed on schedule. Seamless co-operation between Baltic Connector’s project management and the builder, RTA Yhtiöt, is reflected in the results of the work,” commends Herkko Plit, President and CEO of Baltic Connector Oy.
“Good workers and management have a key role to play in ensuring the success of a construction project. The compressor station boasts works management with skills refined over the years in demanding land preparation and construction sites. The worksite has been able to enjoy well-laid plans and excellent co-operation with the developer. As the main contractor, we are responsible for managing this project in accordance with its objectives. We have succeeded in this, and the topping-out ceremony is a milestone in the project’s good progress,” says Nina Lindström, Managing Director of RTA Yhtiöt Oy.
The work at the compressor station started with zone and site preparation in February 2018. Actual construction work of the compressor station began with RTA Yhtiöt in June 2018. Construction work has now progressed to a point where the foundation and structural work of the buildings are, for the most part, completed and the wall and roof units of the buildings are being installed. Process equipment and pipe installation is also underway at the worksite.
“Work has progressed according to schedule and budget. As the work has progressed, the team has become united and the co-operation between the client and the contractors functions very well,” states Mikko Ruokonen, Baltic Connector Oy’s Worksite Manager.
The buildings will be completed in March 2019 for the installation of compressor and automation equipment. After tests in autumn 2019 and once the Baltic Connector project is completed, the station will start operating at the end of 2019.
Read the article online at: https://www.worldpipelines.com/business-news/07112018/baltic-connector-compressor-station-celebration/
You might also like
Summit Midstream announces acquisition of Tall Oak Midstream
Tailwater Capital has announced that it has entered into definitive agreements with Summit Midstream Corporation, whereby Summit will acquire Tall Oak Midstream and its subsidiaries for a total consideration of approximately US$450 million.