Trans Mountain to finish final segment of pipeline expansion in April

Published by , Editorial Assistant
World Pipelines,


Trans Mountain will finish building the final segment of its Canadian oil pipeline expansion in April, according to a construction schedule the corporation filed on Monday 1 April with a regulator, reports Reuters.

The Canadian government-owned CAN$34 billion (US$25.07 billion) pipeline expansion will nearly triple the flow of crude from Alberta to Canada's Pacific Coast to 890 000 bpd, but has been plagued by years of delays, construction problems and cost overruns.

Spread 5-B is the last segment to complete and Trans Mountain's schedule filed to the Canada Energy Regulator shows construction and testing wrapping up this month.

Trans Mountain said last month it has started filling its expanded pipeline in a staged process, but still faced technical challenges.

The pipeline, scheduled to be in service in the second quarter, is expected to raise Canadian crude prices just as producers boost production.

 

 

Read the latest issue of World Pipelines magazine for pipeline news, project stories, industry insight and technical articles.

World Pipelines’ April 2024 issue

The April 2024 issue of World Pipelines includes a keynote section on compliance and standards, along with technical articles on cathodic protection, damage and defect assessment, HDD, integrity and offshore pipelines.

Read the article online at: https://www.worldpipelines.com/business-news/03042024/trans-mountain-to-finish-final-segment-of-pipeline-expansion-in-april/

You might also like

 
 

Embed article link: (copy the HTML code below):


 

This article has been tagged under the following:

Canada pipeline news TransCanada pipeline news


 

World Pipelines is not responsible for the content of external internet sites.