CER recommends approval of NGTL’s Edson Mainline Expansion Project
Published by Aimee Knight,
Editorial Assistant
World Pipelines,
The Commission of the Canada Energy Regulator (Commission, CER) recommends that federal Cabinet approve NOVA Gas Transmission Ltd.’s (NGTL) Edson Mainline Expansion Project (Project). The Project involves the construction and operation of approximately 85 km of natural gas pipeline loops in two sections, along with the associated facilities. The Project is needed to increase pipeline capacity and move gas from the Peace River Project Area to growing markets in central and southern Alberta.
Commissioners heard from more than a dozen intervenors, including industry, federal and provincial government departments and Indigenous peoples. After considering the evidence and submissions presented by all parties, including Indigenous knowledge, the Commission found that the Project is in the Canadian public interest. As part of its recommendation, the Commission included conditions related to, among other things, matters with respect to Indigenous peoples, construction activities, safety measures and standards and environmental monitoring.
Indigenous peoples raised various concerns during the hearing about potential impacts on their rights and interests. The Commission, as part of its response to these concerns, recommended a number of conditions, including requiring a construction monitoring plan for the participation of Indigenous monitors during and post construction. A summary of concerns from Indigenous peoples, responses from NGTL and the Government of Canada, and the Commission's analysis is found in Appendix IV of the report.
The Commission is of the view that, within this Project area, any potential Project impacts on the rights and interests of affected Indigenous peoples are not likely to be significant with the implementation of the mitigation measures and commitments made by NGTL, as well as the conditions and accommodations recommended and imposed by the Commission.
Approximately 73 km (86%) of the pipeline route will parallel the existing NGTL right of way and other existing and proposed disturbances. The Commission noted that NGTL considered input from landowners, occupants, land users, Indigenous peoples and environmental studies in deciding the proposed route.
If federal Cabinet approves this project, the CER will monitor and enforce compliance with all conditions using audits, inspections and other compliance and enforcement tools.
Read the article online at: https://www.worldpipelines.com/project-news/20112020/cer-recommends-approval-of-ngtls-edson-mainline-expansion-project/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Construction begins on Greensand’s carbon dioxide transit terminal at Port Esbjerg
When the tanks are full, the liquefied carbon dioxide will be loaded onto a dedicated carrier from Royal Wagenborg and shipped to the INEOS Nini platform in the Danish North Sea. From there, it will be safely injected via pipeline into subsurface reservoirs approximately 1800 m beneath the seabed for permanent storage.