Line 9 update: Enbridge must conduct more tests
Published by Elizabeth Corner,
Senior Editor
World Pipelines,
The National Energy Board is demanding Enbridge conduct more tests along its 300 000 bpd Line 9 pipeline before the oil can begin to flow, a reversal from just 15 months ago.
In a decision yesterday morning, the NEB said that Enbridge must conduct hydrostatic testing along three sections of pipe between Hamilton, Ontario, and Montreal “to provide the necessary level of confidence in the pipeline’s safe operation.”
Line 9 stretches across some of the most populous parts of the country, running under rivers and tributaries that feed major sources of drinking water like Lake Erie and Lake Ontario.
Hydrostatic testing
Hydrostatic testing involves pumping the pipeline with water at high pressure to test its integrity and seek out leaks and weak points.
The NEB said Enbridge must carry out hydrostatic tests at three locations on the Sarnia, Ontario, to Montreal pipeline. It is also requiring the company to carry out bi-weekly ground patrols and quarterly integrity tests for the first two years of operation for the line.
Edited from various sources by Elizabeth Corner
Sources: The Star, The Globe & Mail
Read the article online at: https://www.worldpipelines.com/project-news/19062015/line-update-enbridge-must-conduct-more-tests/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Oil and gas companies add renewable fuels to low-carbon portfolio, says GlobalData
Share of fossil fuels in the world’s energy mix declined from 82% in 2022 to 81.5% in 2023.