Atlantic Coast pipeline construction to resume
Published by Elizabeth Corner,
Senior Editor
World Pipelines,
Federal officials will allow construction to resume on the Atlantic Coast pipeline, weeks after work was halted when a federal appeals court threw out two key permits for the 600 mile natural gas pipeline, according to a report from CNBC.
The Federal Energy Regulatory Commission announced the change in a letter Monday to Dominion Energy, the project's lead developer, reported CNBC.
Last month, a three judge panel of the 4th US Circuit Court of Appeals concluded that a US Fish and Wildlife Service permit was "arbitrary and capricious" regarding its effect on five threatened or endangered species. Last week, the service issued a revised opinion and the National Park Service issued a new permit for crossing the Blue Ridge Parkway.
The pipeline is planned to start in West Virginia and run through parts of Virginia and North Carolina.
A coalition of environmental groups had asked the federal appeals court to review FERC's approval of the pipeline.
The Southern Environmental Law Center and Appalachian Mountain Advocates petitioned the appeals court on behalf of 13 conservation and environmental groups.
SELC Senior Attorney Greg Buppert said in a statement at the time that the groups believe that FERC "rushed through its decision to permit a pipeline that we don't need."
Pipeline spokesman Aaron Ruby said in a statement Monday that crews would mobilise immediately to resume construction as authorised.
"The Atlantic Coast Pipeline has been the most thoroughly reviewed infrastructure project in the history of our region," he said. "The additional scrutiny we've recently received from the courts and the agencies are further evidence of the high standard that is being applied to the project."
.Read the article online at: https://www.worldpipelines.com/project-news/18092018/atlantic-coast-pipeline-construction-to-resume/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Construction begins on Greensand’s carbon dioxide transit terminal at Port Esbjerg
When the tanks are full, the liquefied carbon dioxide will be loaded onto a dedicated carrier from Royal Wagenborg and shipped to the INEOS Nini platform in the Danish North Sea. From there, it will be safely injected via pipeline into subsurface reservoirs approximately 1800 m beneath the seabed for permanent storage.