Further progress made on the Balticconnector pipeline’s construction
Published by Lydia Woellwarth,
Editor
World Pipelines,
Construction work in the sea for the Balticconnector project offshore pipeline was completed today, Friday 12 July 2019. Pipelaying was finished at the end of June, and the shielding work was begun in mid-June. Now that the shielding work has been finished, all construction work in the sea has been completed. Next, the offshore pipeline will be pressure tested in July - August, after which the pipeline will be emptied and dried.
“We are satisfied that the construction work for the offshore pipeline has progressed on schedule and that we can begin the final phases of the pipeline according to plan. We are progressing at a good pace towards the end of the year when the pipeline will be commissioned,” says Tom Främling, Baltic Connector Oy's Project Director.
The offshore pipeline will be connected to the onshore pipelines in Finland and Estonia during the autumn. The Balticconnector pipeline will be fully ready at the end of 2019, and gas will start to flow in the pipeline on 1 January 2020 as the Finnish gas market opens.
Read the article online at: https://www.worldpipelines.com/project-news/12072019/further-progress-made-on-the-balticconnector-pipelines-construction/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Construction begins on Greensand’s carbon dioxide transit terminal at Port Esbjerg
When the tanks are full, the liquefied carbon dioxide will be loaded onto a dedicated carrier from Royal Wagenborg and shipped to the INEOS Nini platform in the Danish North Sea. From there, it will be safely injected via pipeline into subsurface reservoirs approximately 1800 m beneath the seabed for permanent storage.