Reservation reaches agreement with Enbridge for Line 3 route
Published by Elizabeth Corner,
Senior Editor
World Pipelines,
The Fond du Lac Band of Lake Superior Chippewa has reached an agreement with Enbridge Energy Partners on the replacement of Line 3 through the Reservation.
“We reached this agreement after very extensive work to make sure that the construction and operation of these pipelines best protects the Fond du Lac Band’s needs, rights and interests, and the community at large,” said Kevin Dupuis, Chairman of the Fond du Lac Band. “Our first priority is and has always been to protect our people, our homeland, our Treaty rights, our culture, traditions, and our way of life – ‘inaadiziwin.’ The benefits to the Band far exceed those of potential alternatives, and the agreement was the result of months of extensive consideration and strong advocacy on behalf of the Band.”
The need for this agreement was set in June, when the Minnesota Public Utilities Commission (PUC) approved Enbridge’s applications for permits for Line 3. The PUC also said that they would approve a new route for Line 3 that would go outside of, but very close to, the Fond du Lac Reservation unless the Band and Enbridge reached an agreement that would allow Enbridge to place the line on the current corridor through the Reservation.
The agreement allows Replacement Line 3 to be built along the existing corridor through the Reservation with a comprehensive set of safety, environmental, economic and financial benefits to the Band. These are benefits that would not be possible if Line 3 was built outside the Reservation.
The benefits include:
- Protection of important wild rice waters, lands and natural resources in the 1854 Ceded Territory.
- Removal of the old Line 3 replacing it with a safer pipe and making other needed repairs to other lines.
- With the changes to the pipeline, Band members will have access to wildlife and portions of the Reservation that have been inaccessible.
- Enbridge will comply with Band laws, as well as federal and state laws for environmental protection and safety.
- Compensating the Band for the costs of having the pipelines located through the Reservation.
- Contracting, training and job opportunities for Band members.
The right-of-way through the Reservation will be extended by ten years from its currently scheduled expiration of 2029 – so it will end in 2039. The Band can then re-assess matters regarding the pipeline corridor in consideration of changing times and the Band’s needs and priorities.
Read the article online at: https://www.worldpipelines.com/project-news/03092018/reservation-reaches-agreement-with-enbridge-for-line-3-route/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Construction begins on Greensand’s carbon dioxide transit terminal at Port Esbjerg
When the tanks are full, the liquefied carbon dioxide will be loaded onto a dedicated carrier from Royal Wagenborg and shipped to the INEOS Nini platform in the Danish North Sea. From there, it will be safely injected via pipeline into subsurface reservoirs approximately 1800 m beneath the seabed for permanent storage.