Bulgartransgaz EAD signs contract with Association Consortium Arkad
Published by Aimee Knight,
Editorial Assistant
World Pipelines,
On 18 September 2019, in the presence of the Prime Minister of the Republic of Bulgaria, Mr Boyko Borissov and the Minister of Energy of the Republic of Bulgaria, Mrs. Temenuzhka Petkova, Bulgartransgaz EAD and Association Consortium Arkad signed a contract for the procurement of the necessary materials and equipment, investment design, construction and commissioning of the expansion of the gas transmission infrastructure from the Turkish-Bulgarian to the Bulgarian-Serbian border.
The project for the expansion of the gas transmission system from the Turkish-Bulgarian to the Bulgarian-Serbian border is of strategic significance for Bulgaria. The Energy strategy of the Republic of Bulgaria, following the approval of the National Assembly, has therefore been updated in November 2018.
Bulgartransgaz EAD carries out the necessary actions to implement the project in strict compliance with the effective Bulgarian and European legislation. As part of the concept of the Balkan Gas Hub the expansion of the gas transmission network will boost the energy security of the countries of the region of South East Europe. The Balkan Gas Hub concept expects natural gas from different sources, including the Russian Federation.
On 21 December 2018 Bulgartransgaz EAD announced the procurement procedure for the construction of the linear part stage of the expansion of the gas transmission infrastructure to the Bulgarian-Serbian border – the Balkan Stream.
The procedure has been carried out in line with the Public Procurement Act (PPA) and includes the procurement of the necessary materials and equipment, investment design, construction and commissioning of the expansion of the gas transmission infrastructure starting from the lands of Zlatina village, Provadia municipality, where it links to the existing gas transmission network of Bulgartransgaz EAD to the Bulgarian-Serbian border.
The gas transmission pipeline envisaged for construction is approximately 474 km long, with DN 1200 diameter and 7.5 MPa maximum operating pressure. Together with the construction of the gas transmission pipeline, two optic cable lines will be constructed, which will be laid on both sides of the gas transmission pipeline to the Bulgarian-Serbian border.
The gas pipeline route will cross the lands of 11 districts through which Bulgartransgaz EAD established an easement for its construction.
Within 250 calendar days, a section of about 308 km length will be constructed from Compressor station Polski Senovets, located on the territory of Polski Trambesh Municipality to the Bulgarian-Serbian border, for which Building permits have been issued by the Ministry of Regional Development and Public Works and entered into force.
In the remaining term of the contract - up to 615 calendar days, the rest of the gas pipeline route will be constructed, namely 166 km from Compressor station Polski Senovets to the land of Zlatina village, Provadia Municipality.
In April 2019, Bulgartransgaz EAD selected Consortium Arkad as a Contractor of the public procurement, with whom a contract was signed today.
The signing of the contract is possible after the Supreme Administrative Court terminated the public procurement appeal procedure on 16 September 2019.
The total value of the contract signed today of up to 615 calendar days term of implementation amounts up to over €1.1 billion (VAT excluded).
Read the article online at: https://www.worldpipelines.com/contracts-and-tenders/19092019/bulgartransgaz-ead-signs-contract-with-association-consortium-arkad/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Construction begins on Greensand’s carbon dioxide transit terminal at Port Esbjerg
When the tanks are full, the liquefied carbon dioxide will be loaded onto a dedicated carrier from Royal Wagenborg and shipped to the INEOS Nini platform in the Danish North Sea. From there, it will be safely injected via pipeline into subsurface reservoirs approximately 1800 m beneath the seabed for permanent storage.