Australian court lets Santos build pipeline for Barossa gas project
Published by Isabel Stagg,
Editorial Assistant
World Pipelines,
Australia's Santos can proceed with construction of an undersea pipeline vital to its US$4.3 billion Barossa gas project after a court on Monday 15 January, 2024, ruled in favour of the oil and gas firm in a dispute with an Indigenous man looking to pause the work.
Work on the pipeline, which will connect the Barossa gas field to a processing plant in the northern Australian city of Darwin, was paused by court order in November, 2023, after a suit by a member of an Indigenous group regarded as traditional land owners from the nearby Tiwi Islands.
Simon Munkara sought to halt work and force Santos to do a fresh assessment of the pipeline's impact on underwater cultural heritage. The applicants argued, among other things, that the pipeline would disturb the travels of, and anger, two "ancestral beings" – a rainbow serpent known as Ampiji and Jirakupai, or the Crocodile man.
However, Justice Natalie Charlesworth dismissed Munkara's application and lifted the November court injunction, opening the door for Santos to commence work on the pipeline.
Charlesworth said there was "significant division" among Tiwi Islanders over traditional accounts of Ampiji and Jirakupai and only a "negligible chance that there may be objects of archaeological value in the area of the pipeline route."
Santos shares traded up as much as 3.7% following the decision and then slipped to AUS$7.72, or 2.3% higher at 14:08 (0308 GMT).
Santos welcomed the decision in a statement and said it would continue pipelaying activity for the project.
The Environmental Defenders Office, which represented Munkara, did not immediately respond to Reuters when asked if it would appeal the decision.
The decision clears a major hurdle blocking the long-stalled project and boosts the company's fortunes at a time when shareholders are calling for a meaty premium in a potential merger with larger rival Woodside Energy.
Citi analysts had said a ruling against Santos could delay the vital growth project, where the company aims to start producing gas in the 1H25, by more than a year.
Woodside and Santos announced preliminary talks in December on an AUS$80 billion (US$53.53 billion) tie-up, although the holiday break means a deal is unlikely before February.
The Barossa project, which is co-owned by South Korean energy company SK E&S and Japan's JERA, still needs several environmental plans approved to proceed. A revised drilling plan was approved by the petroleum regulator in December.
Read the article online at: https://www.worldpipelines.com/business-news/15012024/australian-court-lets-santos-build-pipeline-for-barossa-gas-project/
You might also like
World Pipelines Podcast: Going global with IPLOCA
In this episode, Elizabeth Corner speaks to Georges Hage, Executive Secretary at IPLOCA, about IPLOCA's insights on the culture and characteristics of the pipeline contractor community, and how it works to support sustainable energy infrastructure.
Energy industry faces short-term instability, yet remains optimistic about long-term prospects, DNV report reveals
The energy industry is braced for short-term uncertainty caused by global instability, but remains optimistic in the long-term, according to DNV’s annual Energy Industry Insights survey.