CER denies Trans Mountain expansion variance request
Published by Isabel Stagg,
Editorial Assistant
World Pipelines,
The Canada Energy Regulator (CER) on Tuesday 5 December, 2023, denied a request from the Trans Mountain Expansion (TMX) project for a variance on a section of oil pipeline under construction in British Columbia, a decision that could delay the 590 000 bpd expansion.
Trans Mountain had asked to be allowed to install a smaller diameter pipe in a 1.4 mile (2.3 km) section of the oil pipeline's route after encountering "very challenging" drilling conditions due to the hardness of the rock in a mountainous area between Hope and Chilliwack.
The CER denied the variance, according to a letter posted on its website. The regulator said it would give reasons as soon as possible, but had initially issued the decision without reasons because Trans Mountain had asked for an expedited process.
At a hearing on 27 November, Trans Mountain representatives said installing the smaller pipe would save 59 days of construction time and keep the expansion on track for a start date late in 1Q24.
Denying the variance request risked delaying the start date, and drilling a wider section for the larger diameter pipeline to pass through was "unpredictable," Trans Mountain said.
The CER decision is yet another setback for the troubled expansion project, intended to triple shipments of crude from Alberta to Canada's Pacific coast to 890 000 bpd once it starts operating.
Oil market participants in Calgary said the discount on Canadian crude to US benchmark crude widened as a result of the decision.
TMX is due to start shipping oil by the end of March 2024, but a string of construction-related hurdles have fueled concerns the expansion could be delayed.
Trans Mountain, a Canadian government-owned crown corporation, said in a statement it was awaiting reasons for the CER's decision.
"Construction on the Trans Mountain Expansion Project is now more than 97% complete," a spokesperson added.
The CAN$30.9 billion (US$22.78 billion) project, first proposed by Kinder Morgan in 2012, has been beset by years of regulatory delay and cost over-runs and was bought by the Canadian government in 2018 to ensure it was built.
Read the article online at: https://www.worldpipelines.com/business-news/06122023/cer-denies-trans-mountain-expansion-variance-request/
You might also like
The World Pipelines Podcast
Juan Caballero, Chair of the AMPP Board of Directors, talks about AMPP’s global efforts to prevent corrosion and to protect assets, offering insight into how the association listens to its members and serves the pipeline industry.
Listen for free today at www.worldpipelines.com/podcasts or subscribe and review on your favourite podcast app.
Glenfarne and PTT sign cooperation agreement including offtake from Alaska LNG
The Alaska LNG project consists of an 807 mile 42 in. pipeline capable of transporting enough natural gas to meet both Alaska’s domestic needs and supply the full 20 million tpy Alaska LNG export facility.