Skip to main content

Ichthys project completes offshore pipelay

Published by , Editor
World Pipelines,


INPEX CORPORATION (INPEX) has announced that the INPEX-operated Ichthys LNG project safely completed the offshore pipelay for its 890 km, 42 in. dia. gas export pipeline that began in June 2014. It is the longest subsea pipeline in the southern hemisphere and the third longest subsea pipeline in the world.

The gas export pipeline will deliver gas from the Ichthys gas-condensate field to the onshore facilities at Bladin Point near Darwin for processing.

Managing Director Ichthys Project Louis Bon said:

“Completion of the offshore pipelay marks a significant milestone for the project. It means we are one step closer to physically connecting our onshore plant near Darwin to the Ichthys field where our offshore facilities will be permanently moored for the 40 year life of the project.”

The pipeline has been installed by Saipem’s SEMAC and CASTORONE barges from Darwin to the Ichthys field. INPEX will conduct other necessary work on the pipeline in preparation for operational start-up.

Edited from source by Stephanie Roker

Read the article online at: https://www.worldpipelines.com/business-news/05112015/ichthys-project-completes-offshore-pipelay/

You might also like

 
 

Embed article link: (copy the HTML code below):