Skip to main content

NEB welcomes CESD report

 

Published by
World Pipelines,

The National Energy Board (NEB) welcomes the Fall 2015 Report of the Commissioner of the Environment and Sustainable Development (CESD).

The findings and recommendations of the audit reflected areas that the NEB had recognised as needing improvement and will help improve the NEB to better serve Canadians. The NEB has completed work on many of the recommendations and by the end of 2016 will have comprehensively addressed all of the report's findings.

NEB comments

Peter Watson, Chair and CEO, National Energy Board, stated: "The NEB thanks the Commissioner and welcomes the audit's findings and recommendations. The NEB had identified the same areas for improvement and has already completed work on many of the recommendations. An action plan is in place to comprehensively address all of the report's findings by the end of 2016.

"The NEB absolutely enforces and monitors all companies' compliance with pipeline approval conditions and has complete confidence that compliance with pipeline approval conditions is appropriately and comprehensively evaluated by NEB staff and Board members. The audit makes recommendations regarding the documentation of this work and the NEB took immediate action after speaking to the CESD last year to begin rectifying this issue.”

Quick facts

The report makes six recommendations:

  • Four recommendations are about improving NEB documentation processes and data management systems.
  • One recommendation is about consolidating the NEB's risk assessment activities into a central document.
  • One recommendation is about continuing to pursue new ways to meet key staffing challenges.
Edited from source by Stephanie Roker
 

Ongoing Kinder Morgan pipeline projects

An update on Kinder Morgan’s current pipeline projects: Cortez Pipeline, Utopia East pipeline, Trans Mountain pipeline, Sierrita Gas Pipeline, Northeast Energy Direct Project and more.

Tug of war: Energy East pipeline causing a stir

TransCanada's Energy East pipeline project has been causing more debates between politicians, environmentalists and aboriginal groups. Hearings to decide on the fate of the pipeline project are expected in 2016.

KMI vs NEB: the final countdown

Many people have been calling for Canadian Prime Minister Justin Trudeau to postpone Kinder Morgan’s Trans Mountain pipeline hearing, stating that he has not kept his promises regarding pipeline regulatory processes. Soon, the National Energy Board will hold hearings on the project, and by May 2016, the decision on whether to approve it or not should be made.