The National Energy Board (NEB) has issued Board Order MO-01-2016 (Order) that directs NEB-regulated companies to identify and report on the potentially substandard materials being used during pipeline construction and operation. Issuance of the Order is not indicative of an imminent risk to pipeline safety, but rather a proactive measure to enhance pipeline safety.

The NEB is aware of circumstances during which materials used in the production of pipe and pipe fittings do not meet Canadian Standards Association (CSA) or other requirements. The prevalence of their use in Canada is currently unknown.

NEB-regulated companies are required to respond to the Order within 60 days with the following information:

  • Identification of all fittings in use that have been manufactured by Canadoil Asia with production originating in Thailand with specific details regarding the fitting type, grade, year of manufacture and location, products transported and maximum operating pressure.
  • Identification of all Grade 550 fittings in use that have been manufactured by EZEflow Group from 2005 - 2008 with specific details regarding the fitting type, year of manufacture and location, product transported and maximum operating pressure.
  • Detailed mitigation measures and timelines to complete an engineering assessment of pipe or fittings known, or suspected, to have substandard material properties.

Additionally, the NEB has issued two Safety Advisories: Safety Advisory 2016 - 01; Standard for Manufactured Pipe and Fittings and the Potential for Substandard Material Properties and Safety Advisory 2016 - 02; Thermal Expansion Pipeline Design and Operating Considerations.

The Safety Advisories provide guidance to regulated companies and the pipeline industry to address the use of substandard materials that may not meet material standards and to reinforce the need for companies to consider thermal expansion during pipeline design and operation, respectively.

Edited from source by Stephanie Roker

 

NEB welcomes CESD report

The National Energy Board has responded to the oil and gas pipeline oversight audit.

Tug of war: Energy East pipeline causing a stir

TransCanada's Energy East pipeline project has been causing more debates between politicians, environmentalists and aboriginal groups. Hearings to decide on the fate of the pipeline project are expected in 2016.

KMI vs NEB: the final countdown

Many people have been calling for Canadian Prime Minister Justin Trudeau to postpone Kinder Morgan’s Trans Mountain pipeline hearing, stating that he has not kept his promises regarding pipeline regulatory processes. Soon, the National Energy Board will hold hearings on the project, and by May 2016, the decision on whether to approve it or not should be made.