Gazprom Neft connects Badra field to main Iraqi pipeline system

 

World Pipelines,

Gazprom Neft has completed laying, testing and connecting a 165 km oil pipeline from the Badra field, which the company operates in Iraq, to the Gharraf oilfield (Nasiriyah distract, Iraq). With infrastructure already in place at Gharraf, completion of the pipeline from Badra means that the field is now connected to the main Iraqi pipeline system.

The new infrastructure for transporting raw material from Badra has the capacity to transport 204 000 bpd, around 10 million tpy, and can now supply oil to the export terminal at the city of Basra.

The Badra-Gharraf pipeline has two underwater transits, including one covering the river Tigris, and passes over dozens of canals and irrigation systems. For increased operating security, a system to detect leaks and shut off damaged sections and a power supply system running on solar cells will work along the entire length of the pipeline.

Automated systems ensure constant monitoring of the oil transit and real-time management of the pipeline from the Badra field. Gazprom Neft has successfully completed hydrodynamic testing of all sections of the pipeline and the system has been checked for robustness and integrity.

Gazprom Neft produced its first oil at Badra in December 2013 as part of operating tests on well BD4. Work is currently continuing at the site to develop the infrastructure necessary to launch production, which is scheduled for the first half of 2014.

The construction of a central gathering station (CGS) with a capacity of 170 000 bpd is under way. The first CGS line will be coming into operation imminently, with a capacity of 60 000 bpd. Work has also started on a complex gas treatment plant (UKPG) with the capacity to handle some 1.5 billion m3/yr.